The Challenge
The client required the removal of 50mm of deteriorated concrete from a bridge deck without damaging the reinforcement or causing vibration damage to the structure. The project had to be completed within a strict 48-hour window to minimize traffic disruption.
Our Solution
Knights Group deployed two Aqua Cutter 710V robots working in tandem. Our team implemented a high-volume water recycling system to manage waste water in an environmentally sensitive area. Work continued 24/7 in shifts.
Key Outcomes
- Project completed 6 hours ahead of schedule
- 100% of rebar cleaned and preserved
- Zero environmental incidents
- Superior bonding surface achieved for reinstatement
Project Statistics
Concrete Removed45 m³
Timeframe42 Hours
Water Recycled85%
Man Hours320